Building Hawkesbury's Future

We are building Hawkesbury's future

With sealing gravelled roads, constructing new footpaths and building better infrastructure, 2018/19 marks the start of an expanded works program for our Hawkesbury.

Over the next 12 months, we are undertaking major works such as resealing and rehabilitating our roads, upgrading our parks and sporting facilities and improving our community facilities. Additionally, we are commencing a program to seal many of our gravelled roads.

Our 2018/19 Operational Plan (pdf - 12.2 MB) contains the details of our works and we will keep you informed of our planning and progress to deliver these facilities and works as we build Hawkesbury’s future.

The following information on our projects will be regularly updated.

Upcoming Works 2018


  • Park Upgrade Program

    Park Upgrade Program

    Location
    Ham Common, Clarendon
    Description
    We are upgrading park furniture and play equipment in the Ham Common playground precinct
    Commencing:
    September 2018
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Wheelbarrow Ridge Road
    Description
    We are constructing a new culvert to better manage stormwater and protect this road from erosion and storm damage.
    Commencing:
    September 2018
    Project Duration:
    1 week (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Cornwallis Road, Cornwallis
    Description
    We are reconstructing 250m of failed road pavement on Cornwallis Road.
    Commencing:
    September 2018
    Project Duration:
    3 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Open Space Improvements

    Open Space Improvements

    Location
    Bradley Road Reserve, South Windsor
    Description
    We are carrying out improvements to this reserve by piping the open drain and creating more useable spaces for park users.
    Commencing:
    September 2018
    Project Duration:
    3 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Woods Road, South Windsor
    Description
    We are building a new footpath on the north side of Woods Road, between George Street and Collith Avenue
    Commencing:
    September 2018
    Project Duration:
    Approx. 2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Collith Avenue, South Windsor
    Description
    We are building a new footpath on the east side of Collith Avenue, between Woods Road and Harpur Crescent
    Commencing:
    September 2018
    Project Duration:
    Approx. 1 week (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Cox Street, Windsor
    Description
    We are building a new footpath on the east side of Cox Street, between Hawkesbury Valley Way and Windsor Station.
    Completed:
    September 2018
    Project Duration:
    Approx. 1 week (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Mountain Lagoon Road, Bilpin
    Description
    We are reconstructing road pavement on Mountain Lagoon Road, Bilpin
    Commencing:
    August 2018
    Project Duration:
    3 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Ham Street, South Windsor
    Description
    We are reconstructing road pavement on Ham Street, South Windsor
    Completed:
    September 2018
    Project Duration:
    Approx. 1 week (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Mileham Street, South Windsor
    Description
    We are building a new footpath on the west side of Mileham Street, between Campbell and Argyle Street
    Completed:
    August 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Terrace Road, Freemans Reach
    Description
    We are reconstructing road pavement along Terrace Road, Freemans Reach
    Commencing:
    August 2018
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Argyle Street, South Windsor
    Description
    We are building a new footpath on the north side of Argyle Street, between Mileham Street and Macquarie Street
    Completed:
    August 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Bourke Street, Richmond
    Description
    We are building a new footpath on the west side of Bourke Street, between Lennox Street and Joseph Street
    Completed:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Lennox Street, Richmond
    Description
    We are building a new footpath on the south side of Lennox Street, between East Market Street and Paget Street
    Completed:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Paget Street, Richmond
    Description
    We are building a new footpath on the south side of Lennox Street, between East Market Street and Paget Street
    Completed:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Fairey Road, South Windsor
    Description
    We are constructing and sealing Fairey Road, South Windsor, between Speedwell Place and Penruddock Street
    Completed:
    July 2018
    Project Duration:
    4 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    McGrath Road, McGraths Hill
    Description
    The reconstruction of road pavement and shoulder improvements on McGrath Road, between Windsor Road and Old Hawkesbury Road
    Completed:
    July 2018
    Project Duration:
    5 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

Works Completed


Page ID: 112464