Building Hawkesbury's Future

We are building Hawkesbury's future

With sealing gravelled roads, constructing new footpaths and building better infrastructure, 2018/19 marks the start of an expanded works program for our Hawkesbury.

Over the next 12 months, we are undertaking major works such as resealing and rehabilitating our roads, upgrading our parks and sporting facilities and improving our community facilities. Additionally, we are commencing a program to seal many of our gravelled roads.

Our 2018/19 Operational Plan (pdf - 12.2 MB) contains the details of our works and we will keep you informed of our planning and progress to deliver these facilities and works as we build Hawkesbury’s future.

The following information on our projects will be regularly updated.

Works commencing in July 2018


  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Bourke Street, Richmond
    Description
    We are building a new footpath on the west side of Bourke Street, between Lennox Street and Joseph Street
    Commencing:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Lennox Street, Richmond
    Description
    We are building a new footpath on the south side of Lennox Street, between East Market Street and Paget Street
    Commencing:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Pedestrian Connection Program

    Pedestrian Connection Program

    Location
    Paget Street, Richmond
    Description
    We are building a new footpath on the south side of Lennox Street, between East Market Street and Paget Street
    Commencing:
    July 2018
    Project Duration:
    2 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council
    Contractor:
    Savage Earthmoving

  • Road Upgrade Program

    Road Upgrade Program

    Location
    Fairey Road, South Windsor
    Description
    We are constructing and sealing Fairey Road, South Windsor, between Speedwell Place and Penruddock Street
    Commencing:
    July 2018
    Project Duration:
    4 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council

  • Road Upgrade Program

    Road Upgrade Program

    Location
    McGrath Road, McGraths Hill
    Description
    The reconstruction of road pavement and shoulder improvements on McGrath Road, between Windsor Road and Old Hawkesbury Road
    Commencing:
    July 2018
    Project Duration:
    5 weeks (weather dependent)
    Project Manager:
    Hawkesbury City Council